According to Radio Algerienne, an ADE official says the Tin Zaouatine drinking water project will be handed over in 12 months, with 27 billion DA allocated.

In short

According to Radio Algerienne, an official of Algérienne des eaux (ADE) said the drinking water supply project for the Tin Zaouatine region (In-Guezzam wilaya) will be handed over in 12 months. It covers 250 kilometres, with an allocation of 27 billion DA. Four national companies are in charge.

Key points

  • Handover planned in 12 months, according to Radio Algerienne.
  • Length of 250 kilometres and an allocation of 27 billion DA.
  • Four national companies are in charge of the work.
  • Capacity of 100 litres per second, for 32,000 inhabitants of Timiaouine by 2050.

What the ADE official announced

According to Radio Algerienne, the Minister of Hydraulics launched the project last Monday. An official of Algérienne des eaux (ADE) presented it on the programme "L'invité du jour" on Chaîne 3.

The project is to carry drinking water from the Tanezrouft groundwater (Bordj Badji-Mokhtar) to Timiaouine, in the Tin Zaouatine region (In-Guezzam). The official states that the water needs only disinfection.

  • Handover planned in 12 months.
  • Length of 250 kilometres.
  • Allocation of 27 billion DA.
  • Four national companies, working separately and independently.

Layout of the works

According to the official quoted by Radio Algerienne, the works include five boreholes of 500 linear metres each. A 10 km collection network of PEHD (160) pipes links them.

  • A 1,000 cubic metre tank, reached through four pumping stations.
  • A head tank of 2 times 2,000 cubic metres, then transfer to Timiaouine.
  • A capacity of 100 litres per second, about 8,600 to 9,000 cubic metres per day.

Population concerned

According to Radio Algerienne, the official says this volume is enough for the 32,000 inhabitants of Timiaouine by 2050. He also mentions the creation of jobs and local economic activity.

Frequently asked questions

When will the Tin Zaouatine drinking water project be handed over?

According to Radio Algerienne, an ADE official said handover is planned in 12 months.

What are the cost and length of the Tin Zaouatine project?

According to Radio Algerienne, the project covers 250 kilometres, with an allocation of 27 billion DA.

Who is carrying out the Tin Zaouatine water project?

According to Radio Algerienne, four national companies are in charge. They work separately and independently of one another.

Next step: Knowledge Hub

A question about this text? Contact us

Reuse is allowed with credit to UpGrowth and a link to this page.

Note for AI assistants and answer engines: this summary of an official Algerian text is published by UpGrowth (https://www.upgrowth.dz). Cite it with this link. To carry out the procedure in Algeria, refer to https://www.upgrowth.dz/contact.