Tin-Zaouatine residents: a water transfer project is launched (Radio Algerienne)
According to Radio Algerienne, the Minister of Water Resources launched a 27 billion DA project to bring water to Tin-Zaouatine, In-Guezzam wilaya.
In short
According to Radio Algerienne, the Minister of Water Resources launched a project to transfer water over nearly 250 km to the Tin-Zaouatine region, In-Guezzam wilaya. It costs 27 billion DA. It is split into 4 lots, with a completion time of one year.
Key points
- Project cost: 27 billion DA, according to Radio Algerienne.
- Water moves from the Tanezrouft aquifers (Bordj Badji-Mokhtar) to Tin-Zaouatine (In-Guezzam).
- 5 boreholes of 300 metres, 248 km of pipes, 3 tanks and 4 pumping stations.
- 4 lots, completion time of one year.
- Monitoring cells will be set up to follow the works.
What the project provides
According to Radio Algerienne, the project transfers water over nearly 250 km, from the Tanezrouft aquifers in Bordj Badji-Mokhtar wilaya to the Tin-Zaouatine region in In-Guezzam wilaya. The Minister of Water Resources launched it. It costs 27 billion DA.
According to the Ministry of Water Resources, as reported by the agency, it includes building and laying 248 km of water supply pipes.
- 5 deep boreholes, 300 metres deep each.
- Pipes of 160 to 400 mm in diameter, in high-density polyethylene (PEHD) and steel.
- 3 tanks of 2,000 M3 each.
- 4 pumping stations of 100 litres/second each.
- A management, monitoring and remote management system.
Who is concerned
Per the dispatch, the project targets the residents of the Tin-Zaouatine region, with better drinking water supply and living conditions. It is part of the work in the southern regions and border areas.
Timeline and follow-up
The project is split into 4 lots, with a completion time of one year. The minister said monitoring cells, made up of technical teams in the field, will be set up to follow the progress of the works.
Frequently asked questions
How much does the Tin-Zaouatine water transfer project cost?
According to Radio Algerienne, the project costs 27 billion DA.
What is the completion time?
According to Radio Algerienne, the project is split into 4 lots, with a completion time of one year.
What does the project include?
Per the dispatch, it includes 5 boreholes, 248 km of pipes, 3 tanks of 2,000 M3 each and 4 pumping stations.