UpGrowth

Public works in Algeria: DA 980 billion in payment appropriations planned (PLF 2027)

Published on Algerian Radio

According to Radio Algerienne, the 2027 finance bill proposes DA 980 billion in payment appropriations for Public Works and a fund for weather damage.

In short

According to Radio Algerienne, the Minister of Public Works and Basic Infrastructure presented the 2027 finance bill to the finance and budget committee of the APN. The budget proposed for the sector is DA 980 billion in payment appropriations and DA 322 billion in commitment authorizations. The bill also proposes a national fund to repair damage caused by bad weather.

Key points

  • Proposed budget: DA 980 billion in payment appropriations, per Radio Algerienne.
  • DA 322 billion in commitment authorizations, 456 new operations and 14 re-evaluations.
  • Proposal for a national fund to repair damage caused by bad weather.
  • Eastern mining line: 422 km, of which 174 km in operation.
  • North-South rail corridor Algiers-Tamanrasset: 2.036 km in total.

What the 2027 finance bill provides

According to Radio Algerienne, the minister presented the bill to the finance and budget committee of the APN. The budget proposed for the sector is DA 980 billion in payment appropriations.

It also includes DA 322 billion in commitment authorizations, with 456 new operations programmed and 14 others re-evaluated. Commitment authorizations for public investment exceed DA 290 billion. Operating expenses of the services are estimated at more than DA 31,6 billion.

National fund for weather damage repair

According to the same source, the bill proposes creating a national fund to repair damage caused by bad weather. It aims to raise annual financial resources for damage to infrastructure of the sector.

Rail and port projects with figures

Radio Algerienne reports the figures the minister gave on three projects.

  • Eastern mining line: 422 km of electrified double track, 174 km in operation. Technical tests from 13 to 30 October 2026 on a 127 km section. Commissioning planned end of March 2027 for part of the remaining works.
  • North-South corridor Algiers-Tamanrasset: 2.036 km in total. Of 1.925 km: 308 km in operation, 42 km under construction, 924 km in preparation, 651 km at tender.
  • Annaba port: sea wall extended by 1.400 metres, an 82 hectare platform, a new quay 1600 metres long.

Frequently asked questions

What budget is proposed for Public Works in the 2027 finance bill?

According to Radio Algerienne, the proposed budget is DA 980 billion in payment appropriations and DA 322 billion in commitment authorizations.

What does the 2027 finance bill propose on weather damage?

According to Radio Algerienne, it proposes a national fund to repair damage caused by bad weather. It aims to raise annual resources for damage to the sector's infrastructure.

What is the status of the eastern mining line according to the minister?

According to Radio Algerienne, the line runs 422 km and 174 km are in operation. Technical tests run from 13 to 30 October 2026 on a 127 km section.

A question about this text? Contact us

Reuse is allowed with credit to UpGrowth and a link to this page.