Annaba phosphate port in Algeria: progress on the extension works (Radio Algerienne)
According to Radio Algerienne, the Minister of Public Works expressed satisfaction with progress on the extension of the Annaba phosphate port.
In short
According to Radio Algerienne, the Minister of Public Works and Basic Infrastructure expressed satisfaction in Annaba on Thursday with progress on the phosphate port extension. The ore quay extends over 1.600 metres and includes a rear platform of 82 hectares. It is part of the integrated phosphate project.
Key points
- The Minister of Public Works and Basic Infrastructure visited Annaba, according to Radio Algerienne.
- Ore quay: 1.600 metres, with a rear platform of 82 hectares.
- Piling: 1.180 piles out of 1.322 planned.
- Dredging: 11 million m3 out of 13 million m3 planned.
- Rock armour: about 4,32 million tonnes out of 5,5 million tonnes planned.
What the dispatch reports
According to Radio Algerienne, the Minister of Public Works and Basic Infrastructure inspected the project sites in Annaba. He expressed satisfaction with progress on the phosphate port extension and the pace of work on the infrastructure.
The ore quay is part of the integrated phosphate project. It extends over 1.600 metres and includes a rear platform of 82 hectares.
Progress in figures
Radio Algerienne says the minister welcomed the deployment of a second vessel specialised in pile driving work. The figures given on site are as follows.
- Piling: 1.180 piles out of 1.322 planned, at a pace of 7 to 10 piles a day.
- Quay superstructure: 107 reinforced concrete beams laid and 880 precast slabs made.
- Dredging: 11 million m3 of earth excavated out of 13 million m3 planned, with the basin to reach 13 m deep.
- Sea sand fill: about 2,3 million m3 on the rear platform, and a total filled volume above 3,4 million m3.
- Rock armour: about 4,32 million tonnes of stone blocks out of 5,5 million tonnes planned.
- Vibro-compaction and the use of prefabricated vertical drains continue.
Instructions at the end of the visit
According to the same source, the minister stressed the need to keep up the same pace, with stronger coordination between those involved. The aim is to finish the works and deliver the project within the set deadlines.
Frequently asked questions
How long is the ore quay of the Annaba phosphate port?
According to Radio Algerienne, the ore quay extends over 1.600 metres. It includes a rear platform of 82 hectares.
How far has pile driving progressed in Annaba?
According to Radio Algerienne, piling covered 1.180 piles out of 1.322 planned, at a pace of 7 to 10 piles a day.
How far have dredging and rock armour work progressed?
According to Radio Algerienne, 11 million m3 of earth were excavated out of 13 million m3 planned. About 4,32 million tonnes of stone blocks were placed out of 5,5 million tonnes planned.